This set reports measures performed on the 120 MW gas power plant of
Pont-sur-Sambre. The original data have been obtained with a sampling
interval of 10.24 seconds; every subset of 6 samples has been
substituted with their mean value leading to an equivalent sampling
interval of 61.44 seconds.
|
|
|
The mean value has been subtracted from the samples which refer to:
|
|
- Gas flow
- Turbine valves opening
- Super heater spray flow
- Gas dampers
- Air flow
- Steam pressure
- Main steam temperature
- Reheat steam temperature
Source: Dr. J.E.N. Richalet (IFAC identification test case)
|
|
Reference: R.P. Guidorzi, On the use of minimal parametrizations in
multivariable ARMAX identification, 13th IFAC World Congress,
S. Francisco, July 1996.
|
|
|
|